Consistency is key
CIL is designed to contribute towards the funding of local infrastructure, to facilitate sustainable development. This is clearly a desirable outcome, provided the levy is set at a level that does not threaten the viability of the development plan.
Our objective in this report is to seek more consistency in the rate setting process, with particular regard to viability assessment, as the majority of authorities move towards implementation of CIL charging schedules. It is written with our experience of advising and representing members of the Home Builders Federation on appropriate rate setting at a local level across England and Wales.
Within this report, we review the rates at which CIL is being set by charging authorities across the country for the residential development of large greenfield sites, as these are such an important part of national housing land supply. Alongside this, we present a new benchmark for the capacity to pay CIL and Section 106 on such sites, based on a broad view on development economics, local market strength and affordable housing policy.
This paints a picture of the diverse approach that charging authorities are taking to the rate setting process. The result is wide variation in how authorities are striking the balance between fund raising and economic viability, in order to facilitate the scale of development outlined in their Local Plans.
What is the benchmark?
The benchmark is based on the residual development appraisal of a large greenfield site, with generic assumptions relating to significant variables. It gives a starting point for review of policy viability, before examination of local specifics.
How much CIL can be paid?
The National Planning Policy Framework requires that local planning policies should be tested for their viability, such that:
“The sites and the scale of development identified in the plan should not be subject to such a scale of obligations and policy burdens that their ability to be developed viably is threatened. To ensure viability, the costs of any requirements likely to be applied to development, such as requirements for affordable housing, standards, infrastructure contributions or other requirements should, when taking account of the normal cost of development and mitigation, provide competitive returns to a willing land owner and willing developer to enable the development to be deliverable.” (para 173)
The costs of CIL and planning obligations are paid out of land value, as long as there is sufficient value remaining for the land to come forward for development (benchmark land value). If the residual value remaining (after deduction of all costs from total revenues) is too low, then the land is not economically viable to develop, as shown in Graph 1.